
Cofferdam and River Bypass Saves Pipeline Contractor $500,000
Ten-foot cofferdam and river bypass crucial to on-time project completion
View PDFA pipeline construction project replacing a deteriorating 42 inch pipeline more than 20 feet below the surface of a small river met with trouble as unstable shores prevented directional drilling. Rains also brought constantly changing river levels, jeopardizing the final phase of pipeline construction.
Rain for Rent engineered a gravity-fed flume bypass of the river as an alternate to an all-pump bypassing solution, reducing overall bypass costs for the pipeline construction company.
Partnering with Portadam, a 10-foot temporary cofferdam was installed to give the pipeline construction company the additional bracing it needed to complete the drilling project.
The project manager estimated the implemented system saved them $500,000 in bypass pumping costs.
“We were at a standstill and at risk not being able to complete this pipeline project. Rain for Rent’s solution combined with a joint Portadam and Rain for Rent implementation allowed for an on-time project completion under extremely difficult site conditions.”
The cost savings were also seen in the on-time completion of the project that had previous been placed in jeopardy due to the unforeseen stability issues drilling under the river.
Products in
This Case Study
- DV100c 6"x4" PumpView Unit ›
- Portadam™ CofferdamView Unit ›
- Suction HoseView Unit ›
- Discharge HoseView Unit ›